Shaft reactivation at a mine in Ireland. We supplied an articulated headgear system that clears backfill and carries people across four shafts.
- 4 shafts served
- 135 m deepest shaft
- 2 modes, one machine
The challenge
The mine is being brought back into production. When it closed, its shafts were backfilled with pea gravel and crusher dust, with concrete plugs at intervals and discarded core and debris beneath. Before the workings can be re-entered the fill has to come out, using equipment that meets current standards for man riding and conveyance. The client’s first idea was to fit a winch to an excavator and lower a clamshell grab.
Getting started
To start clearing while the main system was engineered, we supplied an airlift clearing system for the first 60 m. Compressed air lifts water and fill up the pipe, a hydraulic agitator head loosens compacted gravel at the bottom and a hopper at surface separates the fill and returns the water to the shaft. It runs from the mine’s own excavator, and clearing ran ahead of the client’s schedule.
One system, two modes
A modified excavator could not be justified as a shaft conveyance. The structure has to carry the breaking load of the wire, and continuous winch duty needs more power and cooling than an excavator can supply. We designed a single articulated headgear system that clears the shaft and carries people. Two winches on an articulating mast lower an electro-hydraulic grab or a man riding cage through interlocked shaft doors. A trailing cable on a constant-tension reeler powers the grab and supplies 110 V for hand tools when the cage is in use. The mast slews to discharge the grab clear of the shaft, folds for road transport and sets up on site without a crane.
Outcome
The mine received a CE-marked, fully interlocked system serving four shafts, the deepest 135 m, with a 1.8 t grab and a man riding cage. It was assembled and tested at our facility in Penryn and shipped in October 2026, on a design and build lead time of under 20 weeks. On uniform fill it is expected to clear a 130 m shaft in about two weeks.